Yes, I can add a mosaic job just fine and it works a treat! But, would it be possible to make a mosaic job in the scheduler, then another one and have it added to the scheduler list? Now it just replaces whatever I put there first.
So is this possible and am I overlooking something? I can only make a mosaic schedule, than add jobs manually, but not 2 mosaic jobs of 2 independent targets which I guess should be possible.
Oh wauw, that was a coincidence in timing. So I create mosaics in the scheduler, save them as a schedule and then I can load them to be attached to the scheduler instead of them being replaced?
edit: So no, indeed manually I can switch but that sort of defeats the purpose of a scheduler.
But I have found a truly manual way to do it.
You can edit the .esl files to combine the jobs.
You need to copy from one to another the sections contained within <Job></Job>
A bit of a hack, but appeared to load everything at once.